Proposed Phase 1 SOW, and the 3-Month Pilot built on it
A revised, role-by-role Phase 1 definition — reconciling the Nov 2025 SOW, the prototype, and CPGS's own questionnaire answers — plus a concrete counter-proposal to the chief's 3-month expectation built on that baseline.
Client
CPGS (Clean & Protect Global Solutions)
Requested by
Gerald Washington, CEO
Constraint
3 months, fixed
Status
Draft — not yet committed
◐All effort and week figures below are illustrative, meant to anchor a conversation — not a committed estimate or contractual timeline. Actual duration depends on team size, the open questions below, and what the chief's deadline is actually driving toward.
Proposed Phase 1 scope of work
What Phase 1 actually means now, role by role — reconciling the Nov 2025 SOW, the prototype, and CPGS's own Pre-Work Questionnaire answers.
◐This section supersedes the Nov 2025 SOW's role definitions. Everything below it on this page — the pilot/full toggle, the comparison table, the open questions — is now built on this baseline, not the original SOW.
Reconciled role model
Role
Who
Platform
Primary purpose
Core functional scope, by role
Cross-cutting requirements
Explicitly deferred beyond Phase 1
Item
Why deferred
Target
Pilot vs. full delivery
Given the scope above, switch between the two delivery paths under discussion.
Dimension-by-dimension comparison
What actually changes between committing to the full SOW vs. carving out a pilot.
Illustrative timeline
Relative scale only — no calendar dates implied.
3-Month Pilot
WEEKS 1–12
Wk 2
Kickoff & setup
Wk 6
Internal test
Wk 10
Client demo
Wk 12
Handoff
Full SOW Phase 1
MILESTONES 1 → 2 → 3DURATION TBD
The SOW itself defines 3 milestones per platform (web + mobile) but states no fixed duration — that absence is itself a signal the original scope was never estimated against a hard deadline.
Open questions blocking a firm estimate
Each of these changes the size of the build — worth resolving with the client before quoting any number, pilot or full.